Construction Updates

CIP 96031- 2021-22 Street Resurfacing (Year 1)


Start Date: Aug 2022

End Date: Spring 2023
Project Manager: Anthony Bendezu Status: In ConstructionProject Location (map)
This project involves the removal of existing pavement and the application of new pavement on various city streets within the southwest side of the city. Also, the project will include concrete work such as the replacement of sidewalk, curb ramps, curbs, and gutters. 

On June, 15, 2022 the city awarded a Public Works Contract to All American Asphalt in the amount of for this project. 


CIP 96036 - SB1 Residential Street Rehabilitation

Start Date: Feb. 2023
End Date: Spring 2023
Project Manager: Ivan DazaStatus: In ConstructionProject Location (map)
The SB1 road improvement project is funded through the Road Maintenance and Rehabilitation Account (RMRA) fund. The work includes cold milling and removal of the existing asphalt pavement and constructing a rubberized asphalt overlay, adjusting utility covers to grade; constructing new ADA curb ramps; repairing residential sidewalk, restoring traffic striping and pavement markings; and providing and maintaining traffic control during construction. Impacted residents may experience temporary traffic control devices, lane closures, detours, parking enforcement and temporary limited driveway access.

On November 16, 2022 the City awarded a Public Works Contract to All American Asphalt in the amount of $869,422 for this project.


CIP 99025 - Monterey Pass Road Water Main

Start Date: March 2023End Date: Fall 2023
Project Manager: Ziad MazboudiStatus: In ConstructionProject Location(map)
This project consists of replacement of a water main pipe along Monterey Pass Road between the intersections of Vagabond Drive and Brightwood street. Recurring water main leaks along this area resulted in extensive infrastructure damage to the roadway and water main pipe repairs are needed to ensure continued water service to residences and businesses in the area. On August 17, 2022, City Council adopted Resolution No. 2022-R69 authorizing the City Manager to take necessary measures for emergency repair. For more information on the project including the current construction schedule, see Monterey Pass Road Project


CIP 95027- Sierra Vista Park Resurfacing

Start Date: March 2023
End Date: April 2023
Project Manager: Anthony BendezuStatus: In ConstructionProject Location(map)
This project consists of resurfacing of existing Pickleball Court and Basketball Court including furnishing/installing new ProDunk basketball system and new pickleball sleeve/posts. 

On February 21, 2023 the City awarded a Public Works Contract to Trueline Construction & Surfacing, Inc in the amount of $26,306 for this project.


CIP 96004- HSIP Cycle 7

Start Date: March 2023
End Date: Summer 2023
Project Manager: Anthony BendezuStatus: In ConstructionProject Location(map)
The HSIP Cycle 7 project consists of Traffic Signal Modifications at Garfield Ave and Emerson Ave; Garfield Ave and Hellman Ave; Alhambra Ave/Almansor St and Hellman Ave, construction of curb ramps, signs and pavement markers, striping and related work. 

On March 2, 2022 the City awarded a Public Works Contract to PTM General Engineering in the amount of $1,030,500 for this project.


CIP 99010 - Emerson Sewer Repair & Pipe Relining

Start Date: March 2023End Date: Spring 2023
Project Manager: Ivan DazaStatus: In ConstructionProject Location (map)
The project consists of rehabilitation of approximately 2,352 linear feet of 8-inch sanitary sewer main using Cured-In-Place Pipe (CIPP) lining method and it also includes spot repairs for approximately 85 linear feet of damaged sanitary sewer pipe.

On December 7, 2022 the City awarded a Public Works Contract to Sancon Technologies, Inc. in the amount of $155,229 for this project.


CIP 96033- Catch Basin Retrofit Device Installation

Start Date: Spring 2023End Date: Summer 2023
Project Manager: Anthony BendezuStatus: In ConstructionProject Location(map)

The catch basin device installation project consists of installing Connector Pipe Screen (CPS) units to city owned and county owned catch basins at various locations. These CPS devices are used to prevent trash from entering the storm drain system during dry weather and moderate storm flows by keeping trash and debris inside the catch basin. Phase 1 included the installation of CPS units in 130 county-owned catch basins. Phase 2 includes installation at an additional 100 catch basin locations. 

On January 18, 2023 the City approved the First Amendment to Public Works Contract with United Storm Water to retrofit an additional 100 catch basins for a revised contract amount of $199,395.


CIP 96034- ATP Cycle 4

Start Date: Spring 2023End Date: Summer 2023
Project Manager: Anthony BendezuStatus: In ConstructionProject Location (map)

The ATP cycle 4 is part of the Active Transportation Program which consists of adding safety enhancements for pedestrians at various locations in the city. This includes restriping of streets, replacing and adding signs, adding solar powered flashing signs for pedestrian crosswalks, and adding ADA compliant pedestrian curb ramp with truncated domes. 

On December 7, 2022 the City awarded a Public Works Contract to California Professional Engineering Inc. in the amount of $1,360,870 for this project.

CIP 96030 - Slurry Seal FY 22-23

Start Date: Spring 2023End Date: Summer 2023
Project Manager : Vivian ChenStatus:Out to BidProject Location(map)
This project will enhance the appearance and drivability of the street and will protect the base of the roadway from water damage and weathering as well as minimize the aging of the existing road and correct raveling and any other defects caused by weather elements. Impacted residents may experience temporary detours and limited driveway access. Please visit the Street Maintenance page for more information on the City's Slurry Seal Program


CIP 96034- HSIP Cycle 9

Start Date: Spring 2023End Date: Fall 2023
Project Manager: Anthony BendezuStatus:Out to BidProject Location (map)

The HSIP Cycle 9 project consists of Traffic Signal Modifications at Garfield Ave, full replacement of traffic poles and mast arms to provide a protected left turn, construction of curb ramps, signs and pavement markers, striping and related work. 


CIP 96035-2021-22 Street Resurfacing (Year 2)

Start Date: Spring 2023End Date: Fall 2023
Project Manager: Anthony BendezuStatus:Out to BidProject Location (map)
This project involves the removal of existing pavement and the application of new pavement on various city streets within the southwest side of the city. Also, the project will include concrete work such as the replacement of sidewalk, curb ramps, curbs, and gutters. 


For more information on a project, please contact the listed project manager or call the Public Works Department at (626)307-1320.