Construction Updates

2019 STREET RESURFACING PROJECT

Monday, November 12 through 

Friday, December 13, 2019 

The City of Monterey Park has contracted with Shawnan Construction to perform street resurfacing and improvements on the roadways listed below. During the construction, temporary lane closures and detours will be in place until the work is completed. Motorists should expect traffic and delays in these areas. 

Affected residents and businesses have been notified.  Thank you for your patience.

NOTE: Revised schedule due to weather, remaining roadways to be rescheduled after Thanksgiving week.

STREET

LIMITS

COLD MILL & LEVELING COURSE


W. Mabel Avenue

Atlantic to Marguerita

Dec 9th & 10th


Marguerita Avenue

Newmark to Garvey

Dec  9th & 10th


Fulton Avenue

North of Wilcox to Kempton Ave

Dec 10th & 11th


Fulton Avenue

South of Wilcox to Kempton Ave

Dec 11th & 12th






Any questions or concerns should be addressed to the Public Works Department at 626-307-1320 during regular business hours, 7:30 a.m. to 5:30 p.m.


WATER MAIN INSTALLATION - NORTH ATLANTIC  

August 21, 2019 - December 13, 2019 

A water main installation project has been approved for the Marriott Courtyard project, at the intersection of Atlantic Boulevard and Hellman Avenue.  During the construction, temporary lane closures and detours will be in place until the work is completed. Motorists should expect traffic and delays in this area.  


Your patience and cooperation are greatly appreciated. Please call the Engineering Division at 626 307-1320 for further information.