City Playground Replacements
Project Manager: Peter Shiau | Start Date: Fall 2023 | End Date: Winter 2024 |
Construction
This project consists of replacing the current playground equipment, site preparation, concrete work, and installation of specialized rubberized surfacing at Bella Vista, Garvey Ranch, Highlands, and Sequoia Parks. New playground equipment will help to improve public safety by replacing aging equipment and repairing any additional issues with the playground equipment or the surrounding areas. The unique designs of each themed playground will help to enhance the usage of the playground users' imagination and foster interaction among the youth in the community. The City is working on completing the work as quickly and safely as possible to minimize the impact to the park visitors.
On August 16, 2023 the City awarded a contract to R.E. Schultz Construction, Inc. in the amount of $986,149 for the construction phase of the project.
Schedule
The project is scheduled to begin in Fall 2023 and is expected to be completed by Winter 2024.
Questions or Concerns
If you have any questions or concerns about this project, please contact the Project Manager, Peter Shiau at (626)-307-1320.
During the design process, playground providers presented playground concepts at the Recreation & Parks Commission meeting in February to gain input and feedback from Commissioners. At the May 1, 2023 meeting, the Recreation and Parks Commission voted unanimously to proceed with the playground designs shown below.
Bella Vista Park (400 Pomona Blvd, Monterey Park, CA 91754)
Dragon Theme
Garvey Ranch Park (781 S. Orange Ave, Monterey Park, CA 91755)
Space Theme
Garvey Ranch Park (781 S. Orange Ave, Monterey Park, CA 91755)
Baseball Theme
Monterey Highlands Park (400 Casuda Canyon Drive, Monterey Park, CA 91754)
Fire Station Theme
Monterey Highlands Park(400 Casuda Canyon Drive, Monterey Park, CA 91754)
Ranger Station Theme
Sequoia Park (750 Ridgecrest Ave, Monterey Park, CA 91754)
Nature Theme
Edison Trails Park Playground Replacement
Project Manager: Peter Shiau | Start Date: Sept 2023 | End Date: Nov 2023 |
Construction
This project consists of replacing the current playground equipment, site preparation, concrete work, and installation of specialized rubberized surfacing at Edison Trails Park. New playground equipment will help to improve public safety by replacing aging equipment and repairing any additional issues with the playground equipment or the surrounding areas. The unique designs of each themed playground will help to enhance the usage of the playground users' imagination and foster interaction among the youth in the community. The City is working on completing the work as quickly and safely as possible to minimize the impact to the park visitors.
On June 7, 2023 the City awarded a contract to R.E. Schultz Construction, Inc. in the amount of $207,272 for the construction phase of the project.
Schedule
The project started in September 2023 and is scheduled to end in November 2023